Thursday, November 17, 2011

Thursday 11/17/2011

The house has many workers frequenting it these days!! There was barely a spot to stop the car and take a pictures... but I did!!

This is from my usual spot facing the property from the front left (?)

Here, I am standing in front of the garage door. You can see the whole for the front door and window to the left of the picture. The guys are standing on the actual floor inside now. They are framing up all the first floor entry ways and windows. The first floor pour is scheduled for Monday 11/21.

Wednesday, November 16, 2011

Wednesday 11/16/2011

Much progress has been made today.
 Here is the house at 12:20 noon
















... and this was at 6:00 PM


















This is the garage
Todd and Larry are working on decking for the sub floor.

This is looking in from the garage into the kitchen. There will be a small hallway to the right leading to the bathroom.

I think they are getting tired of my pictures... but, "Hey this needs to be documented!"

Tuesday 11/15/2011

Things are moving along! They have started to build up the first floor walls and put in the trusses separating the crawl space from the first floor.

MOnday 11/14/2011

The dirt was dropped off today for our patio.

Saturday, November 12, 2011

November 11, 2011

Things are moving quickly!! Our builders from Green Blocks decided they wanted to help out a little more and make sure we get in there as quick as possible... so look at the difference from day 1 to now!!

They just finished the final pour in the first section of walls here.
The portion of blocks you see here is our crawl space. The house had to be raised up 4 feet due to our septic system.
The front needed to be painted to allow for a moisture barrier when they bring the fill on Monday.


Our electricity poll thing will go in soon so we can have electricity on site.. instead of noisy, gas guzzling generators. Luckily our lovely neighbors have been generous enough to let us borrow a bit of their electricity to run a few of the machines. But as you can see there is little waste and minimal electricity necessary. 

On Monday we have 2 truckloads of fill dirt coming and our front porch will be formed up and to be poured on Tuesday. 

Tuesday or Wednesday our friends from Green Blocks will return to put the second set of blocks up to complete the first floor.

Wednesday, November 9, 2011

Day 5

Block Deliver Day!! Early this morning a man in a very large delivery truck was slowly making his way around our neighborhood. I began to wonder if maybe this was our blocks... well, it was!! Poor guy was nervous about backing up onto our property. Luckily Todd was able to run home and help guide him in!

They stacked them up on a truck to bring them to the back of the property.

This is the blocks at the back of the property, technically behind the garage.

The very large truck that delivered our blocks at 8:00 this morning.

The blocks inside the truck.

And by 5:00 this evening we had.............

A partial wall!!

Day 4

Work is moving along...
Today is Wednesday 11/9 and our blocks are being delivered. I already saw our worried delivery truck man sitting at our street waiting for Todd to get here to help guide him in.

Todd will remove all the dirt from our living room area into the front of the house since we had to raise the house up 4 feet due to our septic system. The footers look as if the house will be very small, but Todd has assured me that they always look that way. The slab to the right is our garage.