Thursday, July 7, 2011

So after weeks of waiting...

Again we were waiting for another set of drawings. After a long anticipated time we finally received everything we need to submit everything to the county.

What was holding us up???
* Our septic drawing  (this is not ours, but gives you an idea)
    due to our neighbors having wells in their yards (these are common for sprinkler systems) we had to flip
     flop our house around. So we were waiting on those drawings to be approved.
* Our truss drawings needed to be completed (this is not ours but it gives you the idea)
* and everything else in between!!

 So an update as of today...
*Final drawings are being submitted to county...


So as paperwork is submitted today (7/7/2011) our ICF system is due to arrive on August 1st, 2011!!
         **Update-- due to unforeseen circumstances our paperwork was finally submitted in whole on 7/13/2011***


Rock Solid (our concrete guys) will pour our foundation sometime in the next 2 weeks!!
Todd has assured me that now everything is in the blog updates should come fast and furious with updates. As everything goes up, he will be on site taking all the pictures. So no more Google searches for related images we will actually have images from the work site!!

No comments: