This is from (my usual spot) facing the front door. They are finishing pouring the first floor walls. All first floor windows and doors have been framed up. Tomorrow (Wednesday) they will take off all the bracing. The next step is to put in our second floor trusses, which are about 3 weeks out (approximately). During the mean time the patio should be poured and a few other projects will be tackled.
This is a close up of the right side of the house (facing the street). You can not really see, but the walls are dripping with water from the moisture in the cement.
The 2 sticks coming out of the wall at the top are the marker for where the top of our porch roof will be. The bend re-bar coming out of the ground is where the porch will start. The two large piles of sand/dirt will fill the space up to the bent bars (this is due to our septic system).